Project Description
This IKE modernization project consists of approximately 9 miles of shoulder widening and pavement rehabilitation along U.S. 160 between Oxford and the I-35 interchange. Several reinforced concrete box culverts will be extended such as the Antelope Creek Bridge (071), as well as the replacement of the Arkansas River Drainage Bridge (161). It is currently in the IKE Construction Pipeline with construction planned for 2025. During construction, traffic will be carried through the work zone.
Project Location
Project Details
Project Name | U.S. 160 Shoulder Widening in Sumner County |
Project Number | KA-5805-01 |
Location | U.S. 160: beginning east of I-35 east to Osage Street within the City of Oxford |
Scope | Rehabilitate, add shoulders, replacement of Culvert 555 with the Arkansas River Drainage Bridge (161) and extension of the Antelope Creek Bridge (071) |
Approximate Length | 9.22 miles |
Project Timeline | Construction planned for 2025 |
Construction Cost | $24 million |
Public Meetings
Events
-
U.S. 160 Shoulder Widening in Sumner County Landowner Meeting
12/05/2023 5:30 PM - 6:30 PM