K-96 Improvements

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

Project Description

The K-96 Improvements Project aims to upgrade the K-96 corridor between I-135 and I-35. Improvements are needed to increase freeway capacity, enhance reliability and relieve traffic congestion to keep Kansans moving. 

The project area extends from the K-96 and I-135 interchange (near Hydraulic Avenue) approximately 9.5 miles east/southeast to north of the K-96/U.S. 54/400 interchange. Through traffic engineering studies and environmental review, the project will explore pavement replacement, adding new lanes and includes upgrades to the Hillside, Oliver, Woodlawn, Rock, Webb, Greenwich, and 21st Street interchanges. 

Project Location

Map showing K-96 project area improvements

Project Details

Project Name K-96 improvements
Project Number KA-6099-02
Location Sedgwick County
Scope Upgrade K-96 in Wichita from a 4-lane to 6-lane freeway (pavement replacement only from 21st Street to 13th Street) 
Approximate Length 7 miles
Project Timeline Construction is anticipated to take four years to complete and could begin as early as 2027. After the completion of the Environmental Assessment, the right-of-way process may begin. 

Project Archive

Project Updates

Stay involved and learn more about the K-96 Improvements Project by signing up to receive updates about the project and upcoming events. 

Project Contacts

StaffTitlePhoneEmail
Wilson, JBWichita Metro Public Information Officer(316) 217-0356
Borchers, JakeK-96 Improvements Project Manager(316) 290-9691